Produksi
Produksi
No. | Tahun Penebangan RKT | Target Tebangan | Realisasi Tebangan | Keterangan | ||
| Luas (Ha) | Prod (m3) | Luas (Ha) | Prod (m3) | |||
| 1 | 1971 – 1972 | 800 | 50,000.00 | 400 | 15,456.00 | RKL I |
| 2 | 1972 – 1973 | 1,800.00 | 50,000.00 | 600 | 12,224.00 | |
| 3 | 1973 – 1974 | 1,200.00 | 50,000.00 | 600 | 9,885.00 | |
| 4 | 1974 – 1975 | 1,000.00 | 50,000.00 | 500 | 6,413.00 | |
| 5 | 1975 – 1976 | 800 | 80,000.00 | 600 | 25,000.00 | |
| 6 | 1976 – 1977 | 2,100.00 | 80,000.00 | 900 | 30,000.00 | RKL II |
| 7 | 1977 – 1978 | 800 | 80,000.00 | 800 | 40,000.00 | |
| 8 | 1978 – 1979 | 2,000.00 | 80,000.00 | 800 | 55,000.00 | |
| 9 | 1979 – 1980 | 2,000.00 | 80,000.00 | 1,685.00 | 50,000.00 | |
| 10 | 1980 – 1981 | 1,800.00 | 110,000.00 | 1,500.00 | 89,980.72 | |
| 11 | 1981 – 1982 | 2,200.00 | 30,000.00 | 600 | 29,999.82 | RKL III |
| 12 | 1982 – 1983 | 2,200.00 | 80,000.00 | 750 | 79,998.78 | |
| 13 | 1983 – 1984 | 1,500.00 | 79,000.00 | 1,000.00 | 64,074.96 | |
| 14 | 1984 – 1985 | 2,200.00 | 97,000.00 | 1,400.00 | 56,210.23 | |
| 15 | 1985 – 1986 | 1,600.00 | 80,000.00 | 600 | 33,357.78 | |
| 16 | 1986 – 1987 | 1,800.00 | 80,000.00 | 1,000.00 | 47,592.63 | RKL IV |
| 17 | 1987 – 1988 | 1,600.00 | 80,000.00 | 1,200.00 | 47,829.66 | |
| 18 | 1988 – 1989 | 1,100.00 | 70,000.00 | 900 | 54,630.62 | |
| 19 | 1989 – 1990 | 800 | 50,000.00 | 800 | 49,983.10 | |
| 20 | 1990 – 1991 | 1,000.00 | 50,000.00 | 1,000.00 | 49,502.50 | |
| 21 | 1991 – 1992 | 800 | 40,600.00 | 800 | 40,601.39 | RKL V |
| 22 | 1992 – 1993 | 600 | 47,100.00 | 600 | 47,111.29 | |
| 23 | 1993 – 1994 | 600 | 39,200.00 | 596 | 38,457.14 | |
| 24 | 1994 – 1995 | 600 | 39,200.00 | 452.72 | 28,770.24 | |
| 25 | 1995 – 1996 | 800 | 56,000.00 | 752.12 | 50,411.32 | |
| 26 | 1996 – 1997 | 952.88 | 64,597.53 | 792.6 | 54,504.73 | RKL VI |
| 27 | 1997 – 1998 | 1,097.48 | 64,192.00 | 1,097.48 | 64,072.72 | |
| 28 | 1998 – 1999 | 938.32 | 63,800.00 | 842.76 | 51,502.29 | |
| 29 | 1999 – 2000 | 943.98 | 61,110.00 | 943.98 | 54,926.57 | |
| (April s.d Des) 2000 | 690 | 30,618.00 | 285 | 10,332.59 | Perub dari anggaran ke takwim (Jan – Des) | |
| Jumlah I | 38,322.66 | 1,912,417.53 | 24,797.66 | 1,287,829.08 | ||
No. | Tahun Penebangan RKT | Target Tebangan | Realisasi Tebangan | Keterangan | ||
| Luas (Ha) | Prod (m3) | Luas (Ha) | Prod (m3) | |||
| 31 | 2001 | 807 | 38,400.00 | 398 | 19,168.16 | RKL VII |
| Carry over RKT 2000 | 418 | 15,376.00 | 405 | 14,903.00 | ||
| 32 | 2002 | 640.48 | 33,780.00 | 285.04 | 20,304.95 | |
| 33 | 2003 | 1,055.56 | 39,300.00 | 1,055.56 | 39,360.93 | |
| 34 | 2004 | 1,027.00 | 31,783.00 | 593 | 17,236.69 | TPTI |
| 3,217.00 | 37.02 | 3,226.11 | Trace Jalan | |||
| 35,000.00 | 630.02 | 20,462.80 | ||||
| 35 | 2005 | 998 | 32,810.00 | 511.46 | 18,722.67 | TPTI |
| 2,188.00 | 21.52 | 1,641.66 | Trace Jalan | |||
| 34,998.00 | 532.98 | 20,364.33 | ||||
| 36 | 2006 | 925 | 33,600.00 | 502.56 | 19,412.38 | TPTI |
| 1,400.00 | 16.27 | 1,454.56 | Trace Jalan | |||
| 35,000.00 | 518.83 | 20,866.94 | ||||
| 37 | 2007 | 925 | 24,431.00 | 897.94 | 24,438.81 | TPTI |
| 569 | 27.06 | 577.36 | Trace Jalan | |||
| 25,000.00 | 925 | 25,016.17 | ||||
| RKL VIII | ||||||
| 38 | 2008 | 1,308.00 | 41,268.00 | 669.74 | 22,557.38 | TPTI |
| 232 | 38.6 | 233.71 | Trace Jalan | |||
| 41,500.00 | 708.34 | 22,791.09 | ||||
| 39 | 2009 | 1,208.00 | 23,682.00 | 1,118.76 | 23,172.69 | TPTI |
| 1,318.00 | 64.04 | 1,137.72 | Trace Jalan | |||
| 25,000.00 | 1,182.80 | 24,310.41 | ||||
| 40 | 2010 | 686 | 25,000.00 | 419.3 | 17,840.66 | TPTI |
| 41 | 2011 | 714 | 21,895.00 | 423 | 13,922.35 | TPTI |
| 105 | 23.72 | 104.4 | Trace Jalan | |||
| 22,000.00 | 446.72 | 14,026.75 | ||||
| Jumlah II | 10,712.04 | 370,354.00 | 7,507.59 | 259,416.19 | ||
No. | Tahun Penebangan RKT | Target Tebangan | Realisasi Tebangan | Keterangan | ||
| Luas (Ha) | Prod (m3) | Luas (Ha) | Prod (m3) | |||
| 42 | 2012 | 667 | 21,961.00 | 516.3 | 16,958.98 | TPTI |
| 39 | 13.47 | 38.84 | Trace Jalan | |||
| 22,000.00 | 529.77 | 16,997.82 | ||||
| 43 | 2013 | 1,059.00 | 27,785.00 | 349.9 | 13,391.29 | TPTI |
| 690 | 33.2 | 194 | Trace Jalan | |||
| 28,475.00 | 383.1 | 13,585.29 | ||||
| 44 | 2014 | 1,076.00 | 24,280.00 | 581.5 | 17,284.21 | TPTI |
| 720 | 62.56 | 718.76 | Trace Jalan | |||
| 25,000.00 | 644.06 | 18,002.97 | ||||
| 45 | 2015 | 937 | 24,300.00 | 937 | 24,571.75 | TPTI |
| 685 | – | 685.69 | Trace Jalan ( 33.48 ha) | |||
| 24,985.00 | 937 | 25,257.44 | ||||
| 46 | 2016 | 681 | 16,755.00 | 629.86 | 16,618.87 | TPTI |
| 373 | 19.06 | 373.73 | Trace Jalan | |||
| 17,128.00 | 648.92 | 16,992.60 | ||||
| 47 | 2017 | 1,021.00 | 18,441.00 | 682.4 | 13,183.00 | TPTI |
| 395 | – | – | Trace Jalan | |||
| 18,836.00 | 682.4 | 13,183.00 | ||||
| 48 | 2018 | 741 | 57,334.00 | 203.61 | 12,175.45 | TPTI |
| 13.4 | 395 | 12.81 | 301.35 | Trace Jalan | ||
| 57,729.00 | 216.42 | 12,476.80 | ||||
| 49 | 2019 | 660 | 19,967.00 | 246 | 6,705.13 | TPTI |
| 459 | 31,964.00 | 426 | 29,840.29 | CO | ||
| 25.94 | 380 | 19.34 | 389.28 | Trace Jalan | ||
| 52,311.00 | 691.34 | 36,934.70 | ||||
| 50 | 2020 | 958 | 24,568.00 | 186 | 9,025.45 | TPTI |
| 371 | 13,648.00 | 362 | 12,984.58 | CO | ||
| 38,216.00 | 548 | 22,010.03 | ||||
| 51 | 2021 | 958 | 15,574.55 | 427 | 11,250.10 | TPTI |
| 658 | 10,137.27 | 465 | 8,391.33 | CO | ||
| 10.26 | 143.02 | 10.26 | 143.02 | Trace Jalan | ||
| 25,854.84 | 902.26 | 19,784.45 | ||||
| 52 | 2022 | 906 | 19,322.95 | 655 | 15,877.10 | TPTI |
| 22.04 | 291.98 | 22.04 | 294.66 | Trace Jalan | ||
| 19,614.93 | 677.04 | 16,171.76 | ||||
| 53 | 2023 | 797 | 32,489.29 | 447 | 16,635.96 | TPTI |
| 21.74 | 187.86 | 21.74 | 187.96 | Trace Jalan | ||
| 32,489.29 | 468.74 | 16,823.92 | ||||
| 54 | 2024 | 750 | 28,059.56 | 538 | 20,473.62 | TPTI |
| 236.65 | 32.69 | 239.55 | Trace Jalan | |||
| 28,296.21 | 570.69 | 20,713.17 | ||||
| Jumlah III | 12,792.38 | 390,935.27 | 7,899.74 | 248,933.95 | ||
| Jumlah I +II+III | 61,827.08 | 2,673,706.80 | 40,204.99 | 1,796,179.22 | ||
